Project Construction

The Hard Labor Creek Regional Reservoir Project will be implemented over a 40-50 year period based on cumulative demands and water system growth in Walton, Oconee and the surrounding region.  A tentative schedule for project implementation of Phase I is presented below.

 

Hard Labor Creek Regional Reservoir – Phase I Project Schedule

Phase 1 (Includes Reservoir and 14 MGD WTF)

Start

Completion

Land Acquisition

2005

2013

Reservoir Design/Construction

2013

2015

Reservoir Fills

2015

2016