The Hard Labor Creek Regional Reservoir Project will be implemented over a 40-50 year period based on cumulative demands and water system growth in Walton, Oconee and the surrounding region. A tentative schedule for project implementation of Phase I is presented below. | Hard Labor Creek Regional Reservoir – Phase I Project Schedule | | Phase 1 (Includes Reservoir and 14 MGD WTF) | Start | Completion | | Land Acquisition | 2007 | 2010 | | Reservoir Design/Construction | 2008 | 2011 | | Reservoir Fills | 2011 | 2014 | | Initial Water Treatment/Transmission Systems | 2011 | 2014 |
|